Auckland's City Rail Link Opens Following VINCI-Led Infrastructure Project

Auckland's City Rail Link Opens Following VINCI-Led Infrastructure Project

Auckland's City Rail Link opens following a VINCI-led project, adding 11 km of rail infrastructure and setting a new weekly passenger record.

After years of planning, construction, tunnel excavation, systems installation, and commissioning, Auckland's City Rail Link (CRL) officially opened to the public on 13 September 2026, marking the completion of one of the largest and most complex transport infrastructure projects ever delivered in New Zealand.

The opening represents the culmination of years of collaboration between project stakeholders and the thousands of people who contributed to its delivery.

New Rail Infrastructure and Record Passenger Numbers

The City Rail Link connects Auckland's existing suburban rail network through the city centre, linking Waitematā (formerly Britomart) and Maungawhau (Mount Eden). The project was designed to increase network capacity to up to 24 trains per hour.

The City Rail Link is transforming travel across the Auckland metropolitan area through 11 km of upgraded and new rail infrastructure, including 3.45 km of tunnels beneath the city centre and three major new stations. During its first week of operation, Auckland’s rail network recorded 528,007 boardings, a 62% increase compared with the previous week and a new all-time record, reflecting the public anticipation and benefits delivered by the project.

The City Rail Link project will double the number of people able to travel to Auckland city centre in less than 30 minutes. The new train line is designed to accommodate 54,000 passengers per hour at peak times, equivalent to the capacity offered by two dual 4-lane motorways.

VINCI-Led Delivery and Engineering Challenges

Delivered for City Rail Link Ltd, primarily by the Link Alliance under VINCI's leadership, this project brought together a workforce of up to 2,000 people representing 54 nationalities. The teams overcame significant technical and logistical challenges associated with constructing a modern underground rail system beneath a busy city while minimising disruption to the surrounding urban environment.

The works included the excavation of 3.2 km of tunnels using an earth pressure tunnel boring machine 7.18 m in diameter. Construction also involved maintaining traffic on the North Auckland Line, diverting traffic in Auckland's city centre and operating near existing buildings.

Pierre Bourgeois, civil works director for Asia and Oceania, said: 

“Intended to better serve Auckland city centre and improve mobility for local residents, this is the largest design-build infrastructure project ever carried out in New Zealand.” 

The project was delivered as a fully integrated turnkey railway system, encompassing civil infrastructure, rail systems, signalling, control and communications, as well as testing and commissioning. The successful completion of the City Rail Link marks a significant milestone for urban rail delivery in New Zealand and is expected to provide long-term benefits for Auckland's transport network.


Source

News

Share this page Share on FacebookShare on TwitterShare on Linkedin